- Issued by
- Nepal Water Supply Corporation, Branch Office Hemja
- Contract No.
- 04/NWSCHEMJA/WORK/2081-82
- Work completed
- 2082/08/10
Certified CompletionExcavation, laying and jointing of 110 mm, 90 mm and 63 mm HDPE pipe and 100 mm GI pipe with related fittings, followed by backfilling, stone soling, M15 concrete and premix road reinstatement.
Completed on 2082/08/10, ahead of the 2082/10/11 due date.
More on Water Supply Systems| Description | Unit | Quantity |
|---|---|---|
| Earthwork in excavation | Cum | 3,627.59 |
| Laying and jointing of 110 mm HDPE pipe and fittings | Rm | 1,458.00 |
| Laying and jointing of 90 mm HDPE pipe and fittings | Rm | 3,182.00 |
| Laying and jointing of 63 mm HDPE pipe and fittings | Rm | 1,653.00 |
| Laying and jointing of 100 mm GI pipe and fittings | Rm | 1,200.00 |
| Earthwork in filling | Cum | 3,579.02 |
| Stone soling works | Cum | 31.98 |
| Concrete works, M15 | Cum | 77.34 |
| Reinforcement bar (TOR steel) for RCC works | Kg | 145.13 |
| Reinstatement premix road with base and sub base | Sqm | 140.25 |
Have an infrastructure project we can help with?
Have a question? Call us
+977 9846060963We are located in
Pokhara, Nepal
Kaski · Syangja · Gulmi · Lamjung
Need a quotation? Email us
nishchalnirmansewa@gmail.com